Rinnai Heating Specication Guide 02-13 | 13
Energysaver ueing options
FLUEING OPTION DESCRIPTION FLUE COMPONENTS NEEDED
Direct and direct extended flueing
Direct through-the-wall flueing for walls
75-385 mm thick.
Flue can be extended if wall thickness is
greater than 385 mm using the ESDFK and
additional lengths of ESPIPE900.
A: Direct
- R1350, mushroom flue kit for walls 75-115 mm
- R1351, mushroom flue kit for walls 115-240 mm
- ESDFK
1
, straight horiz. kit for walls up to 385 mm
B: Direct extended
- ESDFK
1
+ ESPIPE900
2
Horizontal (sideways extension) flueing
Flue runs along the left or right hand side
of an internal wall behind the heater.
If retrofitting the flue can be boxed in
along the floor or behind a 125 mm false
wall. This installation requires additional
clearance off the wallback spacer kit
required.
Sideways in-wall
- ESDFK
1
+ ESELBOWB + ESPIPE900
2
Sideways front-of-wall
- Back spacer kit (p. 16) + ESDFK
1
+ ESPIPE900
2
Through-wall (vertical extension) flueing
Flue runs directly from the appliance to
a termination point further up the wall
or vertically to a termination point on
the roof. Typical installation examples
for this type of flue configuration is for
Energysavers installed against solid brick
walls, or where there are flue clearance
restrictions.
A: Vertical termination
- ESDFK
1
+ ESBEND
3
+ ESPIPE900
2
+ ESCONDK +
ESROOFCOWL
B: Horizontal termination
- ESDFK
1
+ ESBEND
3
x 2 + ESPIPE900
2
+ ESCONDK
In-wall (vertical extension) flueing
Flue is installed within a stud wall
(minimum cavity depth of 90 mm) and is
run vertically. This type of installation is
usually completed at the framing stage.
A: Direct
ESKIT03 + ESPIPE900
2
+ ESROOFCOWL
B: Offset
ESKIT03 + ESPIPE900
2
+ ESBEND
3
x 2 + ESROOFCOWL
Down and out flueing
Flue runs below floor level to an
external termination point (must
have a continuous fall of 2 ° to drain
condensate). Ideal for Energysavers that
need to be located in a central position of
a building.
If not going in-wall, flue configuration
requires additional clearance off the
wallback spacer kit required.
Down and out
Back spacer kit (p. 16) + ESDFK
1
+ ESPIPE900
2
+
ESBEND
3
Down and out in-wall
ESELBOWB + ESDFK
1
+ ESBEND
3
+ ESPIPE900
2
Down and out through-wall
4
ESDFK
1
+ ESBEND
3
x 2 + ESPIPE900
2
1
Use terminal off ESDFK on outside wall
2
ESPIPE900, order lengths as required
3
ESBEND kit contains 2 x 45 ° bends
4
Installation that goes out to another room and then down and out